CASE DIGEST: Engineering & Machinery Corp. v. CA


ENGINEERING & MACHINERY CORPORATION, petitioner, vs. COURT OF APPEALS AND PONCIANO L. ALMEDA, respondents

G. R. No. 52267                 |              January 24, 1996

 

DOCTRINE(S): Special Contracts; Prescription

PONENTE: Panganiban

 

FACTS:

Pursuant to the contract dated Sept. 10, 1962, Engineering & Machinery Corp. undertook to fabricate, furnish and install the air-conditioning system of Almeda’s building along Buendia Ave., Makati for P210,000.00. Petitioner was to furnish the materials, labor, tools and all services required in order to so fabricate and install said system. The system was complete in 1963 and accepted by private respondent who paid in full the contract price.

In 1971, Almeda learned that there are defects in the air-conditioning system of the building. He commissioned Engr. David Sapico to render a technical evaluation of the system in relation to the contract with petitioner. In his report, Sapico enumerated the defects of the system and concluded that it was not capable of maintaining the desired room temperature of -2 degree Celsius.

On the basis of this report, private respondent filed on May 8, 1971 an action for damages against petitioner with the CFI of Rizal. The complaint alleged that the air-conditioning system installed by petitioner did not comply with the agreed plans and specifications.

Petitioner moved to dismiss the complaint alleging that the prescriptive period of 6 months had set in pursuant to Art. 1566 & 1567, in relation to Art. 1571 of the Civil Code, regarding the responsibility of a vendor for any hidden faults or defects in the thing sold.

Private respondent countered that the contract dated Sept. 10, 1961 was not a contract of sale but a contract for a piece of work under Art. 1713 of the Civil Code. Thus, in accordance  with Art. 1144(1) of the same Code, the complaint was timely brought within the 10-year prescriptive period.

In its reply, petitioner argued that Art. 1571 of the Civil Code providing for a 6-month prescriptive period is applicable to a contract for a piece of work by virtue of Art. 1714, which provides that such a contract shall be governed by the pertinent provisions on warranty of title and against hidden defects and the payment of price in a contract of sale.

ISSUE(S):

1.       Whether the contract is a contract of sale or a contract for a piece of work

2.       Whether or not the action was filed within the prescriptive period

RULING:

A contract for a piece of work, labor and materials may be distinguished from a contract of sale by the inquiry as to whether the thing transferred is one not in existence and which would never have existed but for the order of the person desiring it. In such case, the contract is one for a piece of work, not a sale. On the other hand, if the thing subject of the contract would have existed and have been the subject of a sale to some other person even if the order had not been given, then the contract is one of sale.

To Tolentino, the distinction between the two contracts depends on the intention of the parties. Thus, if the parties intended that at some future date an object has to be delivered, without considering the work or labor of the party bound to deliver, the contract is one of sale. But if one of the parties accepts the undertaking on the basis of some plan, taking into account the work he will employ personally or through another, there is a contract for a piece of work.

Clearly, the contract in question is one for a piece of work. It is not petitioner’s line of business to manufacture air-conditioning systems to be sold “off-the-shelf”. Its business and particular field of expertise is the fabrication and installation of such systems as ordered by customers and in accordance with the particular plans and specifications provided by customers.

The obligations of a contractor for a piece of work are set forth in Articles 1714 & 1715 of the Civil Code.

In Villostas v. Court of Appeals, the Court held that “while it is true that Article 1571 of the Civil Code provides for a prescriptive period of six months for a redhibitory action, a cursory readying of the ten preceding article to which it refers will reveal that said rule may be applied only in case of implied warranties”; and where there is an express warranty in the contract, as in the case at bench, the prescriptive period is the one specified in the express warranty, and in the absence of such period, “the general rule on rescission of contract, which is four years (Article 1389, Civil Code) shall apply”.

Consistent with the above discussion, it would appear that this suit is barred by prescription because the complaint was file more than 4 years after the execution of the contract and the completion of the air-conditioning system.

However, a close scrutiny of the complaint filed in the trial court reveals that the original action is not really for enforcement of the warranties against hidden defects, but one for breach of the contract itself. It alleged that the petitioner, “in the installation of the air-conditioning system did not comply with the specifications provided” in the written agreement between the parties, “and an evaluation of the air-conditioning system as installed by the defendant showed defects and violations of the specifications of the agreement.

Having concluded that the original complaint is one for damages arising from breach of a written contract – and not a suit to enforce warranties against hidden defects – the Court declared that the governing law is Art. 1715. However, inasmuch as this provision does not contain a specific period, the general law on prescription, which is Art. 1144 of the Civil Code, will apply.  Said provision states, inter alia, that actions “upon a written contract” prescribe in ten (10) years. Since the governing contract was executed on Sept. 10, 1962 and the complaint was filed on May 8, 1971, it is clear that the action has not prescribed.

 


Comments